Three years into a $60 million project to replace the North Hero-Grand Isle bridge in Vermont, crews are pouring concrete with an eye toward building the new replacement drawbridge in the 2022.

The bridge links two islands on Lake Champlain. Progress was slowed earlier by the unexpected discovery of hazardous contaminants, but the materials have been safely removed and work is back on track.

"Things are going well," said Jacqueline Dagesse, spokeswoman of the Vermont Agency of Transportation (VTrans). "We have deconstructed the original drawbridge, constructed the temporary drawbridge now in operation, and we are focused on multiple concrete pours for the bridge substructure. The bridge is on schedule to be operational by May 15, 2022. The project is scheduled to be complete by July 2023."

In recent months, crews with Cianbro excavated lake-bottom sediments from inside the cofferdams and cleaned bedrock in preparation for placing the subfootings for two bascule piers, said Taylor Ware, VTrans resident engineer. Each subfooting was poured via tremie with 1,000 cu. yds. of concrete for each subfooting. Each tremie placement required 13 continuous hours of concrete work. After the bascule pier subfootings were complete, the cofferdams were dewatered and rock anchors installed to withstand buoyant forces on the dewatered cofferdam. Cianbro crews next erected formwork, installed rebar and poured the bascule pier footings, each about 680 cu. yds. of concrete. Once bascule pier footings were complete, they began building the reinforced concrete walls of the bascule piers and supports for the bascule spans.

"The piers are hollow, the equivalent of a three-story reinforced concrete building," Ware said. "The piers will be constructed in three lifts. The contractor is currently working on lift two of each [second story] bascule pier. The two bascule piers will house all of the electrical and mechanical equipment as well as the trunnions and counterweights for the new bascule spans."

Cianbro plans to continue work on the piers through the summer, then begin structural steel erection in the fall.

Earlier this year, crews placed concrete for the second lift of the north horseshoe section and installed reinforcing steel and forms for the south section. On the west side of the existing bridge, the contractor installed formwork and placed concrete for the south horseshoe-shaped section for the second lift of the pier walls. Crews also installed the last of the reinforcing steel and anchor bolts for the north half of the second lift of the pier walls. On the east side of the existing bridge, the contractor installed the last of the reinforcing steel and anchor bolts for the north half of the second lift of the pier walls.

Cianbro currently has two Manitowoc 4100 cranes, FlexiFloat barges and steel concrete forms, which were rented.

The project was held up earlier this year after hazardous materials, including lead, PCBs and hexavalent chromium were discovered during excavation. VTrans engineers believed the contaminants may have come from the sandblasting and painting decades ago of the old bridge railing.

The drawbridge operates only five months of the year, from May 15 to Oct. 15 during boating season. The rest of the year, the bridge remains in the down position to maintain vehicle traffic.

The original historic twin bascule bridge was built in 1953 and was the main road through the island, seeing approximately 3,000 cars daily during the off season and double the number in the summer and fall. The bridge also provides the only unrestricted access for boats and is the only route big sailboats can get through.

The new bridge will have some significant differences from the one it is replacing. Instead of electrical motors that had to be cranked, the new bridge will open and close on a hydraulic system. The new deck will feature stainless steel reinforcement steel, which is anticipated to lengthen the lifespan. Instead of pavement, there will be concrete and the bulk of the girders will be metalized rather than painted, and some smaller pieces will be galvanized. When complete, the new bridge is expected to last 75 to 100 years. CEG

New $840M VA Medical Center Coming to Louisville

University of South Carolina Students Will Benefit from $210M Campus Village

K-Tec Turns a Scraper into a Home

Volvo CE Opens Reservations for Expanded North American Electric Machine Lineup at ACT Expo

Oldest, Youngest Members of AEM Hall of Fame

C.W. Matthews Expects to Complete $111M Phase 2 of Jackson County Project in Coming Months

Briggs JCB Hosts Open House at Its New Tampa Facility

Iron Auction Group Holds Sale at Midland, N.C., Facility

Construction Equipment Guide 470 Maryland Drive Fort Washington, PA 19034 800-523-2200

Construction Equipment Guide covers the nation with its four regional newspapers, offering construction and industry news and information along with new and used construction equipment for sale from dealers in your area. Now we extend those services and information to the internet. Making it as easy as possible to find the news and equipment that you need and want.

Contents Copyrighted 2022, by Construction Equipment Guide, which is a Registered Trademark, registered in the U.S. Patent Office. Registration number 0957323. All rights reserved, nothing may be reprinted or reproduced (including framing) in whole or part without written permission from the publisher. All editorial material, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication and copyright purposes and are subject to Construction Equipment Guide’s unrestricted right to edit and comment editorially. Contributor articles do not necessarily reflect the policy or opinions of this publication. Read our privacy policy here.