May 25—Work on the Grant Street Bridge is at a standstill, delaying completion until late this year.
Kerry Stauffer, Bluefield's engineer, said the delay was caused when engineers found an issue with adequate underground support for the bridge's center pier.
"Unfortunately, the original plan (after the problem surfaced) for the center pier was to drill a casing and then drive piles, but Norfolk Southern consultants did not approve that," he said, explaining that the bedrock was "too soft" to provide enough support for the pilings and that is why the casings were added to the plan.
The consultant only permitted the drive-in piles, not the casings.
Stauffer said the state Department of Highway (DOH) is overseeing the bridge construction and works with the EL Robinson engineering firm, which came up with a plan to install a temporary casing that would be filled with concrete to provide adequate support for the pilings.
Once the pilings are installed, the casings would be removed.
But that plan has not yet been approved by the railroad's consultant.
However, response times related to submitted plans have been "frustrating," he said, as everyone involved awaits the approval.
Brayman Construction is doing the work, Stauffer said they are frustrated as well.
The center pier is a "critical path to the construction of the bridge," he said, and the approval is the holdup.
In the meantime, work could not continue and Brayman crews were sent to other jobs while this issue is being worked out.
City Manager Cecil Marson said the city recently met with Jimmy Wriston, state Transportation Secretary.
"We talked about getting this thing rolling," Marson said, and the DOH is waiting on that approval.
"They have done everything they can try to do to appease the Norfolk Southern consultant," Stauffer said.
Once that approval comes down, work can restart "immediately," he added.
"I am estimating we are about two months behind ... moving the completion date to November or by the end of the year," he said. "Everybody is very frustrated."
The bridge, erected in 1941 to connect the North Side with Princeton Avenue and Downtown Bluefield, was closed in June 2019 after failing a state safety inspection.
After a lengthy quest to find funding to either replace the old bridge or repair it, Gov. Jim Justice in October 2020 announced that a total of $10 million was made available to replace the bridge.
Work started last year and was initially slated to be finished by the end of 2021.
But delays changed the projected completion date to September of this year, which has now been moved to November.
Willie Perry, a resident who lives near the bridge and who has been waiting for a much easier and safer access to the city, thanked Stauffer for the explanation after he had asked city board members why no work had taken place for two weeks.
Perry said it's good that the public knows what is going on with the bridge.
Residents have not had access to that link to the city in almost three years, having to rely on a narrow, winding, hazardous road instead.
Contact Charles Boothe at cboothe@bdtonline.com
He ended his speech praising the National Rifle Association with his trademark "dance" step.
At an Oval Office meeting on school safety, Trump interrupted his advisers’ policy briefing with a rant about the border and his media coverage, a source who was there tells Rolling Stone
Falcons head coach Arthur Smith had well-meaning comments about the Uvalde, Texas school shooting that betrayed a misunderstanding of how politics really work.
Max Schachter, whose son was killed in the 2018 Parkland school shooting, speaks out after Sen. Chuck Schumer blocked a school safety bill named after his son.
A group of four regional lawmakers from Russia’s far east Primorsky Krai have demanded that Russian dictator Vladimir Putin end the war in Ukraine and withdraw Russian troops, Russian newspaper Kommersant reported on May 27.
A pro-Russian resident of the Ukrainian city of Melitopol in southern Ukraine has complained about the behavior of the occupying Russian forces, in a release of an intercepted phone call by the Main Intelligence Directorate on May 27.
The former Heisman Trophy winner is riding Trump's endorsement — and not much else — to a showdown with incumbent Sen. Raphael Warnock
In the wake of a deadly school shooting in his state, Texas Governor Greg Abbott is pointing his finger at Chicago to argue the case for why he opposes stricter gun laws. At a May 25 press conference, the governor said, “I hate to say this, there are more people that are shot every weekend in Chicago than there are in schools in Texas,” Abbott said. “So, if you’re looking for a real solution, Chicago teaches that what you’re talking about is not a real solution.”
Readers share their views on GOP inaction on mass shootings; racist artwork; PSL's recycling goals; and paying school loans
“I can’t believe you’re a sick son of a (expletive) who would come to a deal like this to make a political issue,” Don McLaughlin said to Beto O’Rourke after he disrupted Texas Gov. Greg Abbott’s press conference about the school shooting.
UMM AL-QUWAIN, United Arab Emirates (AP) — The hulking, Soviet-era cargo plane has sat for decades under the blazing sun in a remote corner of the United Arab Emirates, its four jet engines silent after years in the employ of a Russian gunrunner known as the “Merchant of Death.” The emirate of Umm al-Quwain plans a $675 million development on a island just across a lagoon from the deactivated airport where Bout's plane sits.
Chechen leader Ramzan Kadyrov, a staunch ally of Russian President Vladimir Putin, threatened to attack Poland over its support for Ukraine.
A Russian mother told the BBC that her two sons were conscripted into the military and found out later they had been sent to Ukraine.
DENYS KARLOVSKYI - FRIDAY, 27 MAY 2022, 16:57 The Security Service of Ukraine has intercepted telephone conversations between Russian commanders in which they complain about their subordinates refusing to go on the offensive.
Former President Donald Trump offered his solutions to gun violence at an NRA conference held just days after the school shooting in Uvalde, Texas.
The upcoming Georgia senate race is set between Democratic incumbent Sen. Raphael Warnock and Republican challenger Herschel Walker. Walker has agreed to debate Sen. Warnock leading into the election this coming November. However, Warnock has officially committed to three televised debates, according to CBS 46, and touted his accomplishments during his tenure in a statement.
VALENTYNA ROMANENKO - FRIDAY, 27 MAY 2022, 23:20 During the 24 hours of 27 May, the Armed Forces of Ukraine destroyed three Russian air targets and a company-tactical group of the Russian army. Source: Yurii Ihnat, Spokesman of Air Force Command Details: According to the results of the day, the following were hit: Su-35 jet Ka-52 helicopter Orlan-10 UAV a company-tactical group.
"I was misled," Gov. Greg Abbott said. "I am livid about what happened." He spoke after Uvalde police said officers were blocked from the school.
Austrian Chancellor Karl Nehammer said Russian President Vladimir Putin told him on Friday that Moscow would meet its natural gas delivery commitments to Austria and was ready to discuss a prisoner swap with Ukraine. Nehammer made the comments to reporters after the two leaders held a 45-minute telephone call that Nehammer described as a chance to confront Putin with the realities of the war in Ukraine and discuss prospects for humanitarian solutions.
Former Environmental Protection Agency chief Scott Pruitt's corruption knows no bounds